NEW QUESTION 50
An SE is using the output from RVTools to size the storage capacity for a Nutanix Cluster.
Which value most closely resembles the minimum required storage capacity that should be entered for the aggregate workload in sizer?

  • A. 24 TB
  • B. 37 TB
  • C. 15 TB.
  • D. 39 TB

Answer: B

 

NEW QUESTION 51
A customer is asking for a quote for a hybrid cluster to run general purpose VMs and an ERP application containing a 500GB database. The customer has a VSAN ReadyNode quote already and looking for a comparable Nutanix solution. They share the following specifications
3 hosts
2 x E5-2640v4 CPU
512GB RAM
1 x 480GB SSD
2 x 8TB HDD
2 x 1GB NIC
Which two aspects of the requested configuration should cause concern and need for further discovery?
(Choose two.)

  • A. 2 x 1GB NIC
  • B. 512GB RAM
  • C. 2 x E5-2640v4 CPU
  • D. 1 x 480GB SSD
  • E. 2 x 8TB HDD

Answer: A,D

 

NEW QUESTION 52
A prospect needs to refresh their environment but has a very small budget for the project. Four years after their last infrastructure refresh, the prospect's core datacenter is only running at 40% utilization. In addition, they have 25 satelite offices.
Each office has a requirement to run 4 to 6 VMs locally.
Which two Nutanix platform capabilities should the SE hlight to address the prospects concerns? (Choose two)

  • A. Multi-site management
  • B. Pay as you grow
  • C. Automated data storage tiering
  • D. Single node backup
  • E. Software only

Answer: A,B

 

NEW QUESTION 53
A prospect uses VMware, Oracle and Microsoft products for their critical operations. The prospect prefers an all-flash array because they have significantly invested in servers for their oracle environment to save on licensing costs.
Which feature should be discussed to address this objection?

  • A. Hyper-V Support.
  • B. ABS
  • C. AHV
  • D. All-flash nodes.

Answer: B

 

NEW QUESTION 54
A customer previously purchased a Nutanix solution of nine NX-3060 G7 nodes. The customer asks for help to increase the resillency of their environment after power outages to individual racks in their datacenter.
Their current soluction consists of two NX-3460-G7 blocks and a single NX-3160-G7 block placed in a single rack.
What should the systems engineer recommend to this customer?

  • A. Move one node from each NX-3460 block over to the NX-3160 blocks. Enable Block Awareness.
  • B. Buy one additional node and place it into the NX-3160 block, Spread the blocks over three racks. Ebable Rack Awareness.
  • C. Buy three additional NX-3060 upgrade nodes and place them into the NX-3160 block, Enable Rack Awareness.
  • D. Move one node from each NX-3460 block into the NX-3160 block. Spread the blocks over three racks and enable Rack Awareness.

Answer: D

 

NEW QUESTION 55
A customer who uses Nutanix for mission critical workloads is considering migrating public cloud workloads to Nutanix. The customer has experienced difficulty auditing where applications reside and understanding cloud costs on a per application basis.
Which Nutanix product should be discussed to address the customer'sneeds?

  • A. Beam
  • B. Xi
  • C. Calm
  • D. Prism Pro

Answer: A

 

NEW QUESTION 56
During a meeting with a prospect a storage administrator comments that they're currently using 16Gb Fibre Channel for their SAN and believes that 10Gb Ethernet can't provide adequate bandwidth or low latency.
As a followup to the meeting, which Nutanix Bible section would be most helpful in overcoming the storage administrator's objection?

  • A. Do you have any infrastructure refreshes planned for this year?
  • B. Storage Tiering and Prioritization
  • C. Drive Breakdown
  • D. Cluster Components
  • E. Data locality

Answer: E

 

NEW QUESTION 57
A prospects need to refresh their environment but has a very small budget for the project. Four years after their last infrastructure refresh, the prospect's datacenter is only running at 40% utilization. In addition, they have 25 satellite offices. Each office has a requirement to run 4 to 6 VM's locally.
Which two Nutanix platform capabilities should the SE highlight to address the prospect's concerns? (Choose two)

  • A. Automated data storage tiering.
  • B. Pay as you grow.
  • C. Single node backup.
  • D. Software only.
  • E. Multi-Site Management.

Answer: B,E

 

NEW QUESTION 58
A prospective customer has a requirement for Data-at-Rest-Encryption for all their data Which two license options are available to address this requirement? (Choose two)

  • A. Starter with the Encryption SKU
  • B. Pro with the Encryption SKU
  • C. Ultimate
  • D. Pro

Answer: B,D

 

NEW QUESTION 59
CPU utilization climbs above 90% on several VMs. This causes performance degradation for a business-critical application.
How can alerts be configured to notify the administrator before VM CPU utilization hits 90%?

  • A. On a CVM, use ncli to set the VM CPU Check threshold for the critical VMs to a value below 90%.
  • B. On the Health dashboard, locate the VM CPU Check and lower the alert threshold below 90%.
  • C. On the Alerts dashboard, ensure that the VM CPU usage alert is not set to auto-resolve.
  • D. On a CVM, configure a cron job to run the VM CPU Check more frequently and email the result.

Answer: B

 

NEW QUESTION 60
A prospective customer is evaluating solutions to support a project. The systems engineer proposes a hybrid model as recommended by Sizer. The prospect is concerned about the performance of a hybrid configuration and is evaluating an all flash array. Which two Nutanix features should be discussed to address the concerns of the prospective customer? (Choose two)

  • A. Acropolis Dynamic Scheduler
  • B. Automatic Data Tiering
  • C. Data Locality
  • D. AHV Turbo Mode

Answer: B,D

 

NEW QUESTION 61
What are two key Nutanix value propositions? (Choose two)

  • A. Rapid time to value
  • B. Lowest initial cost than a comparable competitive HCI or 3-tier solution
  • C. Highest performance across all workload types
  • D. One-Click Infrastructure Management

Answer: B,D

 

NEW QUESTION 62
A prospect's storage administrator is concerned about deploying Nutanix for their vSphere server virtualization environment due to anticipated increases to data retention for compliance purposes and associated costs.
Which Nutanix feature should an SE discuss to convince the prospect to
move forward?

  • A. Acropolis Block Services
  • B. Adding Storage Only nodes
  • C. Extending storage container with existing SAN storage
  • D. Linear scalability by adding more nodes

Answer: A

 

NEW QUESTION 63
An SE needs to size a new project that requires offsite backup but not remote disaster recovery. The prospect requires an RTO of 48 hours, RPO of 4 hours, and the ability to restore from the past 5days of backups. The prospect's data change rate is 1%.


How should the SE configure Sizer for this scenario?

  • A. Option C
  • B. Option B
  • C. Option A
  • D. Option D

Answer: D

 

NEW QUESTION 64
A System engineer (SE) is gathering requirements to size a hybrid cluster to replace a prospect's existing IT test and development environment. The prospective customer has indicated the cluster contains no business critical applications and has provided the aggregate vCPU and RAM requirements of the existing cluster. which two additional items does the SE require to size the cluster?(Choose two)

  • A. Existing Drive Count
  • B. Working Data Set
  • C. Storage Capacity
  • D. Virtual Switch Configuration

Answer: B,C

 

NEW QUESTION 65
An SE needs to size a new project that requires offsite backup but not remote disaster recovery. The prospect requires an RTO of 48 hours, RPO of 4 hours, and the ability to restore from the past 5days of backups. The prospect's data change rate is 1%.


How should the SE configure Sizer for this scenario?

  • A. Option C
  • B. Option B
  • C. Option A
  • D. Option D

Answer: D

 

NEW QUESTION 66
A customer plans to migrate a business critical, high transaction application to nutanix. Currently the application is running on a physical server with 256GB of RAM and 12 CPU cores at > 80% utilization. To run the VM on a single NUMA node, which processor configuration should the systems engineer recommend for this workload?

  • A. CPUs (8 Cores each @ 2.1Ghz), 16 Cores total
  • B. CPUs (8 Cores each @ 1.8Ghz), 16 Cores total
  • C. CPUs (10 Cores each @ 3.4Ghz), 20 Cores total
  • D. CPUs (16 Cores each @ 2.8GHz), 32 Cores total

Answer: C

 

NEW QUESTION 67
A two-node ROBO cluster is configured with a witness VM.

What happens when Node A goes down?

  • A. The- cluster becomes unavailable and goes into read-only mode.
  • B. The cluster is unaffected and no administrator intervention is required.
  • C. All operations and services on the Node B are shut down and go into a waiting state.
  • D. Node B sends a leadership request to the Witness VM and goes into single-node mode.

Answer: D

 

NEW QUESTION 68
A systems engineer is creating a workload for a sizer Scenario that requires Disaster Recovery (DR) resources with a Recovery Point Obiective (RPO) of 6 hours. The "Protect VMs and other Entities" setting is set to Yes. Async is selected for the RPO.
Which two other options must be enabled to have Sizer create a DR cluster? (Choose two)

  • A. Disaster Recovery
  • B. Backup
  • C. Remote SnapShot
  • D. NearSync

Answer: A,C

 

NEW QUESTION 69
Which two statements are true regarding SAP?

  • A. SAP is certified on Nutanix NX, Lenovo HX and Dell XC hardware.
  • B. Nutanix is a SAP Global Technology Partner.
  • C. Due to SAP certification requirements, no Nutanix SAP reference architectures are available.
  • D. SAP Sybase DB is only supported on IBM Hyperconverged Systems powered by Nutanix.

Answer: A,B

 

NEW QUESTION 70
What is the main function of Oplog?

  • A. A memory cache to coalesce burst of random write before destaging to the extend store.
  • B. A persistent write buffer to coalesce bursts of random writes before destaging to the extend store
  • C. A memory cache to coalesce all writes before destaging to the extent store.
  • D. A persistent write buffer to coalesce all write before destaging to the extend store.

Answer: B

 

NEW QUESTION 71
Using the Sizing Option shown, which two configurations are possible configurations that Sizer could provide in Automatic mode? (Choose two) ????

  • A. 6x NX-8055-G7 (2 x 7.68TB SSD + 10x 6TB HDD per node)
  • B. 3x NX-3060-G7 (2x 1920GB SSDs per node) + 3x NX-10755-G7 (4x 3.84TB SSDs per node)
  • C. 4x NX-1075S-G7 (4x 3.85TB SSDs per node) + 4x NX-8035-G7 (6x 3.84TB SSD per node)
  • D. 6x NX-3060-G7 (6x 1920GB SSDs per node)

Answer: B,D

 