NEW QUESTION # 17
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- B. The activities occur in series with a 15-day lag.
- C. The activities run concurrently.
- D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
Answer: B
NEW QUESTION # 18
Under which circumstance should one perform resource-leveling calculations?
- A. When you believe that known resource limitations may override schedule logic.
- B. When the contract contains a provision for float-banking.
- C. When the schedule is resource-loaded.
- D. Never, unless required by the contract.
Answer: A
NEW QUESTION # 19
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS.2003 + 1 day -> 10-07-01.
- B. LS.2003 - 1 day -> 10-06-01.
- C. LS.2003 - 1 day -> 11.06.01.
- D. LS.2003 - 1 day -> 10-05-01.
Answer: D
NEW QUESTION # 20
What is the result of a forward pass calculation?
- A. Value of free float for individual activities
- B. Critical path
- C. Value of total float for individual activities
- D. Early start and early finish date for individual activities
Answer: D
NEW QUESTION # 21
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-28-01.
- B. 09-18-01.
- C. 09-15-01.
- D. 09-08-01.
Answer: D
NEW QUESTION # 22
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 0 days.
- B. 5 days.
- C. 10 days.
- D. 15 days.
Answer: A
NEW QUESTION # 23
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
- A. Is a milestone.
- B. It is on the critical path.
- C. Has yet to be completed.
- D. Was completed in the past.
Answer: C
NEW QUESTION # 24
Free float is the
- A. Difference between the early finish dates and late finish dates of an activity.
- B. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
- C. Difference between the early dates and late dates of an activity.
- D. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.
Answer: B
NEW QUESTION # 25
Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?
- A. 9001 and 6002 and 6002
- B. 1000. 1001. and 6001
- C. 1000 and 6001
- D. 1001 and 6001
Answer: A
NEW QUESTION # 26
What owner action could have mitigated the late completion of the project?
- A. Self-perform more of the work.
- B. Use a procurement agent to monitor and expedite equipment deliveries.
- C. Hire a more senior project manager.
- D. Prepare better structural steel drawings.
Answer: B
NEW QUESTION # 27
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?
- A. 193 days
- B. 91 days
- C. 183 days
- D. 168 days
Answer: C
NEW QUESTION # 28
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. The schedule is projecting an "early completion".
- B. The schedule has too much detail to reflect an accurate critical path.
- C. Certain activities in the critical path have no successors.
- D. Different calendars are assigned to certain activities in the logical chain.
Answer: A
NEW QUESTION # 29
What is the cycle time?
- A. 5 minutes
- B. 14 minutes
- C. 6 minutes
- D. 17 minutes
Answer: D
NEW QUESTION # 30
What is the free float for Activity F?
- A. 0months.
- B. 2month.
- C. 3 months.
- D. 1months.
Answer: A
NEW QUESTION # 31
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 5 days.
- B. 0 days.
- C. 10 days.
- D. 15 days.
Answer: A
NEW QUESTION # 32
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
- A. The regulations published by the government aviation agency
- B. The project geotechnical report
- C. The government's report on future high-clearance bridge projects
- D. The project plans and specifications
Answer: C
NEW QUESTION # 33
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project contract between the contractor and owner
- B. Project deliverables
- C. Project objectives in terms of cost, schedule and quality measures
- D. Project justification
Answer: D
NEW QUESTION # 34
A driving relationship is _____________________.
- A. A finish-to-start relationship.
- B. A critical relationship.
- C. The link between a predecessor and the activity whose dates it controls.
- D. The link between two related activities.
Answer: C
NEW QUESTION # 35
Identify the late finish to develop plans and specs.
- A. 9 months.
- B. 8 months.
- C. 10 months.
- D. 7 months.
Answer: A
NEW QUESTION # 36
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.
PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.
Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
- A. $307,000.
- B. $420,000.
- C. $524,000.
- D. $552,000.
Answer: D
NEW QUESTION # 37
The data date or status date of a schedule represents the:
- A. date the monthly update is performed
- B. system date when the software calculates the update
- C. date the project manager turns in the schedule update
- D. date on which progress is based
Answer: A
NEW QUESTION # 38
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Collapsed As-Built.
- B. Periodic Windows.
- C. Time Impact.
- D. Gantt Chart.
Answer: D
NEW QUESTION # 39
......